Rezoning is one of the most consequential steps in any land development project. It determines what you can build, how dense your development can be, and which uses are permitted on your property. If your proposal requires a different zoning classification than what currently exists, a rezoning application is the path forward.
But for many developers and landowners in Kelowna, the rezoning process feels opaque. What exactly happens after you submit? Who reviews your application? How does neighbourhood consultation work? What does it take to actually get to a Council decision?
This guide walks you through the entire rezoning application process in Kelowna, step by step, based on the City’s current procedures and our experience managing development applications across the Okanagan. Whether you’re applying for the first time or looking for a clearer picture of what’s ahead, this is the roadmap.
Before You Begin: Do You Actually Need a Zoning Amendment?
Not every development project requires rezoning. In Kelowna, every property has a zoning classification under the Zoning Bylaw that determines what’s currently permitted, including land uses, density, building height, setbacks, and lot coverage. If your proposed development fits within the existing zoning, you may only need a development permit or building permit.
You need a rezoning application when your proposal requires a change to the zoning classification, for example, changing from single-family residential (RU1) to allow multi-family development (RM3), or from one commercial zone to another to permit different uses.
Critical distinction: every property also has a future land use designation under the Official Community Plan (OCP). If your proposal doesn’t align with the OCP designation, you’ll need an OCP amendment in addition to the rezoning. This significantly extends the process, so confirming OCP alignment is one of the very first things you should do.
You can check your property’s current zoning and OCP designation using the City of Kelowna’s online Map Viewer.
Step 1: Research Your Property and Develop Your Concept
Estimated timeline: 1–3 months
Before engaging consultants or preparing an application, do your homework. This foundational research phase sets the direction for everything that follows.
Start by confirming the property’s current zoning classification and OCP land use designation. Review the Zoning Bylaw to understand what’s currently permitted and what zone you’d need to rezone to. Check whether there are Development Permit area guidelines that apply to the site, such as hillside development, form and character, or natural environment requirements.
Assess the site itself, topography, access, servicing availability, environmental constraints, and any other factors that could influence your development concept. If the property is within or adjacent to the Agricultural Land Reserve (ALR), there may be additional provincial requirements to address.
This is also the time to develop a preliminary development concept that’s informed by policy context, not just market ambition. Proposals that align with the OCP, support the City’s growth management priorities, and respect neighbourhood context have a significantly smoother path through the approvals process.
Ascend tip:
Developers who invest time understanding City priorities and policy direction before submission consistently move through the formal review process faster. This research phase is where strategic planning pays off.
Step 2: Attend a Pre-Application Meeting with City Staff
Estimated timeline: 2–4 weeks to schedule and attend
The City of Kelowna offers pre-application meetings where you can sit down with planning staff to discuss your proposal before you formally submit. This is one of the most valuable steps in the entire process, and one that too many applicants skip.
During the meeting, staff will review your concept and provide feedback on potential policy alignment issues, required technical studies, neighbourhood consultation expectations, and any concerns they can identify early. They can also confirm whether your proposal requires just a rezoning or an OCP amendment as well.
Come prepared with a preliminary site plan and a clear description of what you’re proposing. Take detailed notes on everything staff recommend. The guidance you receive here becomes your roadmap for assembling the application. You can contact the City’s Planner of the Day at [email protected] or 250-469-8626 to arrange a meeting.
Ascend tip:
Treat this meeting as non-negotiable. We’ve seen a single pre-application conversation prevent months of delay that would have resulted from submitting without understanding the City’s expectations.
Step 3: Assemble Your Consultant Team and Prepare the Application
Estimated timeline: 1–2 months
Based on what you learned in the pre-application meeting, you’ll now need to engage qualified professionals and prepare your submission package. Depending on the complexity of your project, this may include a planner, civil engineer, geotechnical engineer, environmental consultant, traffic engineer, land surveyor, and architect or designer.
Your application package will typically include the completed City application form and fees, a project description and rationale explaining how the proposal aligns with OCP policies, a site plan and conceptual drawings, and all required technical studies and supporting reports. The specific studies required vary by site and project, but may include a traffic impact assessment, servicing analysis, geotechnical report, environmental assessment, stormwater management plan, and archaeological overview.
The quality and completeness of this initial submission is critical. Applications that are returned or placed on hold due to missing information can lose months. Every report should be reviewed for consistency with the others before the package is filed.
Ascend tip:
Establish a single point of coordination for your consultant team. Someone needs to be responsible for aligning scopes, managing timelines, reviewing deliverables, and ensuring the package tells a cohesive story. This is the core of what a development manager does.
Not sure if your application is ready?
Download our Free Development Approvals Readiness Checklist to assess your project before you submit. Or book a consultation to talk through your approvals strategy with our team.
Step 4: Submit Your Application to the City of Kelowna
Once your application package is complete, submit it to the City’s Development Planning department at City Hall. The City will confirm receipt, process your application fee, and assign your file to a planning staff member who becomes your file manager for the duration of the review.
Your file manager is your primary point of contact at the City. They coordinate the internal and external review of your application, communicate comments and requirements back to you, prepare the staff report to Council, and guide the file through to a decision. Building a professional, responsive relationship with your file manager is one of the most important things you can do throughout this process.
Note that incomplete applications are not accepted by the City. Ensure all required forms, documents, and fees are included before you submit.
Step 5: City Staff and Agency Review
Estimated timeline: 1-2 months (first round)
After submission, your application enters the City’s formal review process. This involves review by multiple internal departments, including planning, development engineering, utilities, parks, fire, and transportation, as well as external referrals to agencies such as the School District, Interior Health, the Regional District of Central Okanagan (RDCO), FortisBC, and others as applicable.
Each reviewing body assesses your application against their specific mandate and requirements. The result is a set of staff comments identifying issues, requesting clarification, imposing conditions, or asking for additional information or revisions. Your file manager will compile these comments and send them to you.
The timeline for this phase varies significantly depending on the City’s current workload, the complexity of your application, and the number of referral agencies involved. During busy periods, first-round review can extend to four months or longer.
Ascend tip:
Don’t wait passively during review. Maintain proactive communication with your file manager. Regular check-ins help you understand review priorities, clarify questions before they become formal comments, and demonstrate your commitment to moving the file forward.
Step 6: Respond to Review Comments and Resubmit
Estimated timeline: 1–3 months per round
When you receive staff and agency comments, this is where responsiveness matters. Review each comment carefully, coordinate with your consultants to prepare revisions or additional information, and resubmit a comprehensive response that addresses every item.
Partial responses or slow turnarounds are one of the most common causes of extended timelines. Each resubmission cycle adds a minimum of four to eight weeks as staff re-review the updated materials. Applications that require multiple rounds of revisions due to incomplete responses can add several months to the overall timeline.
The goal is to address all comments thoroughly and completely in a single response wherever possible. If any comments are unclear, reach out to your file manager for clarification before you begin revisions rather than guessing at what’s being asked.
Step 7: Complete Neighbourhood Consultation
Estimated timeline: 1–3 months
Every rezoning and OCP amendment application in Kelowna requires neighbourhood consultation as outlined in Council Policy #367. The City sends notification letters to surrounding property owners, and you as the applicant are expected to engage with the community about your proposal.
Your consultation package should include a clear site plan showing what you’re proposing, a description of the project, and contact information for your file manager at the City. Depending on the scale and impact of your project, you may also be expected to host a public information session or open house.
Consultation done well is an opportunity, not a burden. Hearing concerns early allows you to address them proactively, sometimes through design adjustments, sometimes through clear communication that resolves misunderstandings. Strong community engagement builds support that carries through to the Council stage. Poor engagement, or none at all, creates opposition that can delay or derail your application.
Ascend tip:
Start neighbourhood engagement early, even before the formal City requirements kick in. Developers who invest in transparent, proactive dialogue with the surrounding community consistently have smoother paths through the public process.
Step 8: Staff Report and Council Consideration
Estimated timeline: 1–2 months
Once the review process and neighbourhood consultation are complete, your file manager prepares a report to Council with a recommendation of either support or non-support for your application. This report summarizes the proposal, the review findings, public feedback, and the rationale for the staff recommendation.
Initial consideration occurs at a Monday afternoon Council meeting. If staff recommend support for your application, you typically won’t be asked to speak at this meeting. Council reviews the staff report and decides whether to advance the application to the bylaw reading stage.
Council agendas are scheduled well in advance, so even when your file is ready, you may need to wait several weeks for an available meeting date. Understanding the Council calendar and planning your submission timing accordingly helps manage expectations.
Step 9: Public Notification, Bylaw Readings, and Adoption
Estimated timeline: 1–3 months
Under changes to the Local Government Act, rezoning applications that are consistent with the OCP are no longer required to go through a public hearing unless Council specifically directs one. Instead, there is a 10-day public notification period after initial consideration and before the first reading of the bylaw. During this period, the public can contact Development Planning for information or write to Council.
If an OCP amendment is required, a public hearing is still mandatory. Council hears directly from the applicant and members of the public before proceeding.
After the notification period (or public hearing, if applicable), Council considers giving first, second, and third readings to the bylaw at a Monday afternoon meeting. After third reading, it’s the applicant’s responsibility to meet any requirements outlined in the Council resolution, such as registering covenants, providing security, or completing other pre-conditions, before the application can advance to fourth reading and final adoption.
Most straightforward applications receive all three readings within four to six weeks if Council is supportive and there is minimal opposition. Complex or contested applications may see delays between readings.
Step 10: Fulfill Conditions and Advance to Final Adoption
Estimated timeline: Varies (typically 2–8 weeks)
After third reading, Council’s resolution will outline any conditions that must be met before the bylaw can be finally adopted. These may include registering restrictive covenants on title, providing landscaping or security deposits, completing servicing agreements, or fulfilling other requirements specific to your application.
Once all conditions are satisfied, the bylaw advances to fourth reading and final adoption. At this point, your property is officially rezoned and you can proceed to the next stages of your development approvals, which may include development permits, subdivision applications, building permits, or servicing agreements depending on your project.
Ascend tip:
Rezoning adoption is a milestone, not a finish line. Plan your next approvals stages in advance so there’s no gap in momentum between rezoning completion and your next application.
What Comes After Rezoning?
Rezoning is one component of the broader development approvals process. Depending on your project, you may still need to complete development permit applications for form and character, building permit applications, subdivision applications and approving officer review, servicing agreements and development cost charge payments, and building construction and occupancy permits.
Each of these stages has its own timeline and requirements. The total time from rezoning application to construction start often runs 18 to 30 months or longer for complex projects. Having a clear phased strategy from the beginning, one that anticipates how these stages sequence and overlap is essential to keeping your project on track.
Navigating the Process with Confidence
The rezoning process in Kelowna is detailed and multi-staged, but it’s navigable especially when you approach it with a clear understanding of what’s required at each step. The developers and landowners who move through approvals efficiently share common traits: they do their research, submit complete applications, communicate proactively with City staff, engage their communities transparently, and respond rapidly when action is needed.
At Ascend Development Partners, this is the work we do every day. We guide developers and landowners through the full spectrum of development approvals in Kelowna and across British Columbia from building your initial approvals strategy through consultant coordination, application management, and ongoing support through to adoption. If you’re planning a rezoning application and want experienced guidance on navigating the process, we’d welcome the conversation.